There has been a flurry of activity on the outdoor classroom/pavilion build. We have made a lot of progress this month in completing the pavilion’s foundation in addition to starting the framing of the trusses. The Pavilion’s architect, Victor A. Mirontschuk, FAIA, with EDI International, visited the build site during the first week of July. He reviewed the work done so far with our building committee and conferred with our Builder, Kelly Gross. Victor also took aerial photos with his drone and documented the builds progress.

Our outdoor classroom build is moving forward after being delayed temporarily by a delay in the shipment of the large timbers from Canada. Our wet summer and the installation of utilities, such as electricity to the remote site, have also been challenges to our builder and building committee. We are now on track to finish the framing this next week and start the rock work before the middle of the month. Please enjoy our picture gallery below and stay tuned for updates on our project!